Company Logo

Heritage Property Repairs

Listed Building Restoration Specialists

Menu
  • Home
  • Services
    • Lime Repointing
    • Lime Works
    • Leadwork
    • Lead Welding Subcontract
    • Traditional Roofing & Guttering
    • Chimney Damp
    • Stone Masonry & Repairs
    • Heritage Brickwork
    • Sympathetic Façade Cleaning
    • Reports & Investigations
    • Decoration
  • Case Studies
  • About Us
  • Testimonials
  • Contact Us
Menu

Case Studies:
Grade I Listed Church

exterior elevation of works
Posted on December 1, 2021January 31, 2022 by HPR

St Mary Church on the outskirts of Lancashire dates back to 1157AD, with its South Aisle added in the 14th century.

We won the tender for works identified during the Conservation Architect’s Quinquennial inspection. These consisted of:

  1. Internal lime patch re-plastering of the main Church walls.
  2. External lime repointing of the Stone built Porch.

1. Internal Lime Plastering

The internal lime plastering works were to two high level areas of the original main church. The interior walls of the Church had been plastered and whitened, likely around the 16th century Reformation lead by King Henry VIII.

The original lime plaster had failed in two areas. The loose had been removed by others and left exposed for a period of monitoring. As there was no evidence of water ingress, we gained permission from the Conservation Architect to replaster, agreeing a three coat hot (quick) lime mix. The base and float coat included grit sand and animal hair for binding, with the finish coat only including fine sand.

We sheeted the floors and pews with protective coverings and carefully erected an internal access tower. The preparation included rebuilding a section of loose stonework – which we believe to have been the original cause of the plasterwork failing.

Each coat of lime plaster was left a number of days to take prior to the next coat, during which we focused on the external works. Once completed, we limewashed the new works to blend with the whitened walls of the Church.

2. External Porch Lime Repointing

The Quinquennial inspection also identified early delamination damage to the historic stonework of the South Aisle Porch. This was caused by non-porous cementitious mortar forcing moisture to evaporate through the stone face.

External works were carried out in-between the internal lime plaster coats.

We carefully removed the existing mortar from the wide joints, and flushed out any debris. We deep filled and packed with a hot (quick) lime mix featuring grit sand for aggregate content. The same mix was used for the finish face pointing.

We sheeted over the porch with hessian and covers to keep the lime moist and protected, until it was ready to be brushed back and exposed. Upon brushing back, we endeavour to leave no brush marks and expose the aggregate in the mortar.

Acknowledgements

We scheduled around funerals and weekly mass, which are some of the functions that we respectfully anticipate when working on Churches.

Everyone involved with the Church were extremely kind and appreciative throughout the project. The volunteers’ passion and dedication to run and upkeep the property was clear to us each day.

The Church fundraises to pay for any works that become required, regularly opening at weekends to take donations for cakes and drinks.

  • church porch in sunlight
    Exterior of Porch Before
  • damage to internal church wall
    Existing damage to high level plaster
  • internal damage to church wall
    Existing damage to high level plaster
  • inside church with scaffold tower
    Lime Plaster in Progress
  • church porch partially repointed
    Porch Repointing In Progress
  • internal arches of church
    Completed Lime Plastering
  • close up of external lime mortar
    Completed lime repointing (brushed back with aggregate showing)
  • repointed exterior of church porch
    Completed Repointing to Porch
  • exterior elevation of works
    Completed Porch

Latest Case Studies

  • Tower Door RestoredRe-Staining of Grade I Listed Church Doors
    May 24, 2025
  • Lime Plastering onto Cork BoardsCork Board Insulation
    March 8, 2025
  • Completed Drone PhotographLime Repointing Farmhouse
    January 31, 2025
  • CompletedFormer Mill Lime Repointing
    December 22, 2024
  • Completed and Finish PaintedBlackpool Balustrade Replacement
    November 30, 2024

View more case studies...

©2025 Heritage Property Repairs Ltd

heritagepropertyrepairs@gmail.com

07415 435 938

Privacy Policy